HOST: City of Miami Beach, Office of Capital Improvement Project (CIP)
Location: Residential roadways within San Marino, DiLido and Rivo Alto islands. This project does not include the Venetian Causeway.
Public Information: Yaisel Gonzalez, 305-345-7269 or yaisel.gonzalez@qcausa.com
Project Purpose and Timeline:
Neighborhood improvements to the rights of way and infrastructure upgrades are in progress. When completed, the area will be better prepared to overcome sea-level rise flooding with a brand new, state-of-the-art drainage system. The project, scheduled for completion by the end of 2016, includes the following scope of work:
- Existing sanitary sewer lining (complete)
- New water mains and electronic meter reader (complete)
- New storm water drainage system (work in progress)
- Installation of concrete vally gutters ( work in progress)
- Full-depth roadway reconstruction (work in progress)
- Street lighting (work in progress)
- Spot sidewalk repair